What is the normal project completion time


Questions:

Critical path for project at normal completion time

1. What is the critical path for this project at normal completion time?

A. A-E-G
B. B-E-G
C. A-D-G
D. C-F-G

2.What is the normal project completion time?
A. 25 weeks
B. 10 weeks
C. 4 weeks
D. 14 weeks

3. Which activity on the critical path has the lowest weekly crash cost?
A. A
B. B
C. C
D. D
E. G

4. What is the crash cost per week for activity G?
A. 2000
B. 1500
C. 1000
D. 250

5. Write the mathematical representation of the objective function to minimize the crash cost for this project.

6.What is the mathematical representation for the crash time constraint of activity D?
A. YD<=7
B. YD<=3
C. YD<=4
D. YD<=5000

7. In the linear program to crash this project, why would activity G require two network constraints?
A. The difference between the normal time and the crash time is 2 weeks
B. G has two predecessor activities
C. The crash cost is 2000
D. all of the above

8. Use either CPM crashing of the LP method to calculate this: What is the total extra cost to the company for completing this project in

9. weeks with minimal crashing expenses?
A. 1000
B. 1600
C. 400
D. 600

 

Solution Preview :

Prepared by a verified Expert
Mathematics: What is the normal project completion time
Reference No:- TGS01919641

Now Priced at $20 (50% Discount)

Recommended (99%)

Rated (4.3/5)