What is the network diagram calculate the slack for each


A project for improving a billing process has the following precedence relationships and activity times :

Activity

Activity Time(weeks)

Immediate Predecessor(s)

A

5

-

B

9

-

C

6

A

D

12

B,C

E

9

B

F

5

D

G

3

E

h

6

F,G

What is the network diagram?

Calculate the slack for each activity. Which activites are on the critical path?

project for improving a billing process has the following precedence relationships and activity times Activity Activity Time (weeks) immediate Predecessor(s) B, C 12 F, G

Request for Solution File

Ask an Expert for Answer!!
Operation Management: What is the network diagram calculate the slack for each
Reference No:- TGS02672124

Expected delivery within 24 Hours