What is the net present value of this project 104089 100328


Rent-to-Own Equipment Co. is considering a new inventory system that will cost $750,000. The system is expected to generate positive cash flows over the next four years in the amounts of $350,000 in year one, $325,000 in year two, $150,000 in year three, and $180,000 in year four. Rent-to-Own's required rate of return is 8%. What is the net present value of this project? $104,089 $100,328 $96,320 $87,417