What is the net present value of a project that requires a


What is the net present value of a project that requires a net investment of $59,000 and produces net cash flows of $19,000 per year for 7 years? Assume the cost of capital is 15 percent.

Select one: a. $ 20,047 b. $ 15,520 c. $ 19,000 d. $59,000

Show calculations using Excel.