What is the net present value npv of the


Green Forest Consulting is evaluating a project that would cost 4,290 dollars today. The project is expected to produce annual cash flows of 516.95 dollars forever with the first annual cash flow expected in 1 year. The cost of capital associated with the project is 10.52 percent and the project’s internal rate of return is 12.05 percent. What is the net present value (NPV) of the project?