What is the minimum cycle time for the completion


Discuss the below:

Use the following information:

TASK

TASK TIME (SECONDS)

IMMEDIATE PREDECESSOR

A 40 -
B 12 A
C 9 B
D 18 -
E 22 D
F 17 E

1) What is the minimum cycle time for the completion of this process?

2) How many full items can be produced in a work day (7 hours and 15 minutes)? This must be a whole number (round down if necessary).