What is the minimum cycle time for completion of process


Assignment:

Please answer the question Only if you know the right answer and no internet answer

- Use the following information:

TASK

TASK TIME (SECONDS)

IMMEDIATE PREDECESSOR

A 40 -
B 12 A
C 9 B
D 18 -
E 22 D
F 17 E

1) What is the minimum cycle time for the completion of this process?

2) How many full items can be produced in a work day (7 hours and 15 minutes)? This must be a whole number (round down if necessary)

Request for Solution File

Ask an Expert for Answer!!
Operation Management: What is the minimum cycle time for completion of process
Reference No:- TGS02125065

Expected delivery within 24 Hours