What is the minimum cost of crashing the following project


What is the minimum cost of crashing the following project by 4? days? (Please explain and SHOW ALL WORK)

Activity Normal Time (days) Crash Time (days) Normal Cost Crash Cost Immediate Predecessor(s)
A 6 5 $900 $1,000 -
B 8 6 300 400 -
C 4 3 500 600 -
D 5 3 900 1,200 A, B
E 8 5 1,000 1,600 C