What is the minimum cost of crashing the following project


What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days?

Activity

Normal Time (Days)

Crash Time (Days)

Normal Cost

Crash Cost

Immediate Predecessor(s)

A

6

5

$900

$1,000

-

B

8

6

300

400

-

C

4

3

500

600

-

D

5

3

900

1,200

A

E

8

5

1,000

1,600

C

Request for Solution File

Ask an Expert for Answer!!
Operation Management: What is the minimum cost of crashing the following project
Reference No:- TGS02156938

Expected delivery within 24 Hours