What is the minimum cost of crashing the following project


1. What is the minimum cost of crashing the following project by 3 days?

Activity

Normal Time (days)

Crash Time

(days)

Normal Cost

Crash Cost

Immediate Predecessor(s)

A

6

5

$ 900

$1,000

-

B

8

6

300

400

-

C

4

3

500

600

-

D

5

3

900

1,200

A, B

E

8

5

1,000

1,600

C