What is the maximum output this assembly process could


Problem : Theory of Constraints

The manufacturing company you work for has a four step assembly process shown in the flow diagram below.

Process 1

Capacity =

80 units/hr

Process 2

Capacity =

60 units/hr

Process 3

Capacity =

70 units/hr

Process 4

Capacity =

50 units/hr

What is the maximum output this assembly process could produce in 10 hours?

If the capacity of Process 1 is increased to 90 units/hour, how many units can be assembled in 10 hours?

If the capacity of Process 4 is increased to 90 units/hour, how many units can be assembled in 10 hours?