Theory of Constraints

process 1=80 units/ hr

process 2=60 units/hr

process 3=70 units/hr

process 4=50 units/hr

What is the maximum output this assembly process could produce in 10 hours?

If the capacity of Process 1 is increased to 90 units/hour, how many units can be assembled in 10 hours?

If the capacity of Process 4 is increased to 90 units/hour, how many units can be assembled in 10 hours?