What is the maximum allowable set up time assuming there is


A manager wishes to produce a product at the rate of 20 unites per hour from a machine. The processing time per unit product is 2 minutes on the machine. The batch size to be used must be 50. What is the maximum allowable set up time assuming there is no waiting at the machine?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: What is the maximum allowable set up time assuming there is
Reference No:- TGS02260824

Expected delivery within 24 Hours