What is the materials price variance for the month and what


The standards for product K17 call for 5.0 meters of a raw material that costs $19.10 per meter. Last month, 2,700 meters of the raw material were purchased for $51,435. The actual output of the month was 460 units of product K17. A total of 2,500 meters of the raw material were used to produce this output.

Required:

a. What is the materials price variance for the month?

b. What is the materials quantity variance for the month?

Solution Preview :

Prepared by a verified Expert
Accounting Basics: What is the materials price variance for the month and what
Reference No:- TGS0786297