What is the makespan


Assignment:

Sequence the jobs shown below by using a Gantt chart. Assume that move time between machine is one hour. Sequence the jobs in priority order 1,2,3,4.

(A) what is the makespan?

(B) how much machine idle time is there?

(C) when is each job delivered compared with its due date?

(D) how much idle time waiting time is there for each job?

Job work center machine   DUE DATE

1 A/3, B/2, C/2                  3

2 C/2, A/4                        2

3 B/6, A/1, C/3                  4

4 C/4, A/1 B/2                   3

Solution Preview :

Prepared by a verified Expert
Operation Management: What is the makespan
Reference No:- TGS02963399

Now Priced at $25 (50% Discount)

Recommended (97%)

Rated (4.9/5)