What is the latest finish and latest start for all


Environmental Recycling, Inc. must clean up a large automobile tire dump under a state environmental cleanup contract. The tasks, durations (in weeks), cost, predecessor relationships are shown as follows:

Activity

Predecessor(s)

Normal Time

Crash Time

Normal Cost

Crash Cost

A

-

5

4

$400

$750

B

A

8

6

1600

2200

C

A

7

6

800

1100

D

-

6

5

600

1000

E

B, D, C

8

6

1200

2200

F

D

3

2

800

1000

G

D

3

2

500

650

H

E

4

3

400

600

I

F, G, H

6

5

900

1300

What is the Earliest start and Earliest finish for all activities left to right?

What is the Latest Finish and Latest start for all activities right to left?