What is the impact of the revised estimates for finalized


Question: What is the impact of the revised estimates for Finalized Product Design and Install Production Equipment on the project schedule and cost? Would you recommend authorizing the expenditure of $50,000? Explain. What, if any other recommendations, would you make so that the project can achieve Robin's deadline? Justify your recommendations.Include a Tracking Gantt chart with variance schedule that depicts your final recommendations and revised schedule. Hint: After adjusting the Installation of Production Equipment and Finalized Product Design, level outside of slack to eliminate any resource over allocation problems.