What is the impact of the revised estimates for finalized


What is the impact of the revised estimates for Finalized Product Design and Install Production Equipment on the project schedule and cost? Would you recommend authorizing the expenditure of $50,000? Explain. What, if any other recommendations, would you make so that the project can achieve Robin's deadline? Justify your recommendations.Include a Tracking Gantt chart with variance schedule that depicts your final recommendations and revised schedule. Hint: After adjusting the Installation of Production Equipment and Finalized Product Design, level outside of slack to eliminate any resource over allocation problems.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: What is the impact of the revised estimates for finalized
Reference No:- TGS02422423

Expected delivery within 24 Hours