What is the flow rate of the process per hour


Discuss the below:

Q: The local driver's license center processes applications for driver's license renewals through the following three steps.

First, the customer registers with one of 5 receptionist(s), who updates the customer's information in the database. This first step takes 7 minutes per customer. Then the customer visits one of 2 cashiers to pay the associated fees for the license renewal. This takes 4 minutes per customer because several forms must be printed from the computer and signed by the customer. Finally, the customer visits one of 4 license processing stations where the customer's picture is taken and the license is printed. This final step takes 4 minutes per customer.

Assuming unlimited demand, what is the flow rate of the process per hour in customers per hour?

Assuming unlimited demand, what would the new flow rate be if the center added one server to the bottleneck resource?

Request for Solution File

Ask an Expert for Answer!!
Microeconomics: What is the flow rate of the process per hour
Reference No:- TGS02038150

Expected delivery within 24 Hours