What is the expected time to complete the project


You are a project manager in Company Ltd. and are assigned a new project that consists of nine major activities. These activities and their immediate predecessors, as well as the activity time estimates (in days) are:

Activity

Immediate predecessor

Optimistic

Most probable

Pessimistic

A

-

3

5

6

B

-

2

4

6

C

A, B

5

6

7

D

A, B

7

9

10

E

B

2

4

6

F

C

1

2

3

G

D

5

8

10

H

D, F

6

8

10

I

E, G, H

3

4

5

1) What are the critical activities?

2) What is the expected time to complete the project?

3) What is the probability that the project can be completed in 25 days or fewer?

Solution Preview :

Prepared by a verified Expert
Basic Statistics: What is the expected time to complete the project
Reference No:- TGS0688825

Now Priced at $10 (50% Discount)

Recommended (93%)

Rated (4.5/5)