What is the expected project completion time


Problem 1: Given the following network project:

Activity

Estimated Time (mo.)

Immediate Predecessor

A

10

-

B

12

-

C

15

-

D

18

A

E

7

C

F

9

B,C

a. Develop a network diagram.

b. How long will it take to complete the project?

c. Which activities are on the critical path?

d. How much stack is in each activity?

e. What is the impact on the critical time if the time for activity A is increased to 14 months?

Problem 2)  Given the following network project:
 

Activity

Estimated Time (days)

Immediate Predecessor

A

2

-

B

3

-

C

4

-

D

2

A,B

E

1

C.D

F

3

A

G

5

F

H

2

C

I

4

E,G,H

J

7

I

K

3

J


a. Develop a network diagram.

b. How long will it take to complete the project?

c. Which activities are on the critical path?

d. How much stack is in each activity.

e. What is the impact on the critical time if the time for activity B is reduced by two days?

Problem 3)  Given the following network project with multiple time estimates in weeks:

Activity

Optimistic

Modal

Pessimistic

IP

A

10

14

16

-

B

12

12

12

-

C

6

10

12

A

D

5

8

9

B

E

10

12

14

C,D

a. What is the expected project completion time?

b. Identify the critical path(s).

c. Describe each of the task distributions as either skewed right, skewed left, normal or constant.

d. What is the probability that the project will exceed 32 weeks?

e. What is the probability that the project can be completed within 34 weeks?

Solution Preview :

Prepared by a verified Expert
Other Management: What is the expected project completion time
Reference No:- TGS01768376

Now Priced at $25 (50% Discount)

Recommended (94%)

Rated (4.6/5)