What is the expected estimated time for activity h what is


Kimmy Gibbler, President Gibbler Industries, has developed the tasks, durations, and predecessor relationships in the following table for building new stores. Draw the AON network and answer the questions that follow.

ACTIVITY

IMMEDIATE PREDECESSOR(S)

TIME ESTIMATES (IN WEEKS)

 

OPTIMISTIC

MOST LIKELY

PESSIMISTIC

 

A               

---

5

9

12

B

A

4

9

20

C

A

9

15

14

D

A

5

9

8

E

B

5

6

8

F

E, C

3

6

5

G

E, C

6

7

20

H

F

5

6

4

I

F

3

4

5

J

D, G, H

5

4

13

K

I, J

5

3

2

  • What is the expected (estimated) time for activity H?
  • What is the variance for activity H?
  • Based on the calculation of estimated times, what is the critical path?
  • What is the estimated time of the critical path?
  • What is the activity variance along the critical path?
  • What is the probability of completion of the project before week 34?

Solution Preview :

Prepared by a verified Expert
Business Management: What is the expected estimated time for activity h what is
Reference No:- TGS01693418

Now Priced at $30 (50% Discount)

Recommended (96%)

Rated (4.8/5)