What is the expected completion time of the project


Problem:

The following table represents a project that should be scheduled using PERT.

Required:

Question 1) What is the expected completion time of the project?

Activity

Immediate Predecessor

Times (Days)

a

m

b

A

None

1

3

5

B

A

1

2

3

C

A, B

2

3

4

D

C

3

4

5

a. 10 days

b. 11 days

c. 12 days

d. 9.5 days

Solve the problem and show all work.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: What is the expected completion time of the project
Reference No:- TGS0884254

Expected delivery within 24 Hours