What is the expected completion time for the project


Problem:

Job Number

Predecessor Jobs

a

m

b

1

-

2

3

4

2

1

1

2

3

3

1

4

5

12

4

1

3

4

11

5

2

1

3

5

6

3

1

2

3

7

4

1

8

9

8

5,6

2

4

6

9

8

2

4

12

10

7

3

4

5

11

9,10

5

7

8

Required:

Question 1) Construct the appropriate network diagram

Question 2) Indicate the critical path

Question 3) What is the expected completion time for the project?

Question 4) You can accomplish any one of the following at an additional cost of $1,500

(1) Reduce Job 5 by two days

Reduce Job 3 by two days

Reduce Job 7 by two days

If you will save $1,000 for each day that the earliest completion time is reduced, which action, if any, would you choose and why?

e. What is the probability that the project will be completed in 30 days?

Solve the given numerical problem and illustrate step by step calculation.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: What is the expected completion time for the project
Reference No:- TGS0880298

Expected delivery within 24 Hours