What is the equivalent evm schedule variance sv schedule


You are responsible for analyzing and quantifying cost and schedule performance on an Agile life cycle development project. During planning for the first sprint, the development team decided on a sprint duration of 15 days and estimated they could complete 30 story points during the sprint. The development teams consists of five people with an aggregate daily cost of $500. Assume this is the daily sprint cost.

Note: Story points represent about equal amounts of work and are a way of estimating the scope of a product backlog item based on size and complexity. A large and/or complex product backlog item is worth more story points than a smaller and/or less complex product backlog item.

At the end of 10 days, the development team has completed only 17 story points. What is the equivalent EVM Schedule Variance (SV), Schedule Performance Index (SPI), Cost Variance (CV), and Cost Performance Index (CPI)?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: What is the equivalent evm schedule variance sv schedule
Reference No:- TGS02941007

Expected delivery within 24 Hours