What is the ending balance of work in process on june 30


Tara Aldrin installs outdoor water gardens. On June 1, Tara had three jobs in process, for the Fazels, Myrons, and Pattons, with the following costs:

 

Fazel

Myron

Patton

Direct materials

$ 560

$  270

$1,200

Direct labor

900

700

1,000

Applied overhead

     270

      210

     300

Total

$1,730

$1,180

$2,500

During the month of June, two more jobs were started, the Raider and Willis houses. Materials and labor costs incurred by each job in June are as follows:

 
Materials
Direct Labor

Fazel

$600

$1,200

Myron

350

980

Patton

260

650

Raider

780

1,350

Willis

725

900

The Fazel and Myron jobs were completed and billed by June 30.

Required

1. If overhead is applied on the basis of direct labor dollars, what is the overhead rate?

2. Prepare simple job-order cost sheets for each of the five jobs in process during June.

3. What is the ending balance of Work in Process on June 30? What is the cost of jobs sold in June? (Round your answers to the nearest dollar.)

4. Suppose that Tara prices her jobs at cost plus 40 percent. In addition, during June, marketing and administrative costs of $1,200 were incurred. Prepare an income statement for the month of June.

Request for Solution File

Ask an Expert for Answer!!
Managerial Accounting: What is the ending balance of work in process on june 30
Reference No:- TGS01258358

Expected delivery within 24 Hours