What is the duration of the critical path of this network


Problem

1. What is the duration of the critical path of this network

2. What is the float for activity G

3. If a project manager proposes a finish time of 14 on teh project with no change in the start or activity durations, what is the total float of activity E.

 

Activity

Duration

Predeoesors

2

A

2

 

3

B

6

 

4

C

4

2,3

5

D

1

4

6

E

3

555

7

F

1

3

3

G

5

3

3

H

1

7,8

10

I

2

6,9

 

Request for Solution File

Ask an Expert for Answer!!
Computer Engineering: What is the duration of the critical path of this network
Reference No:- TGS02739918

Expected delivery within 24 Hours