What is the direct labor quantity variance in


You have this data for a product made by Evans Company

Direct Labor Standards are

Quantity standard: 2 hours

Price Standard $24 per hour

2,000 units were produced in July.

During July, the company actually used 4,200 hours of direct labor at an actual price of $24.40 per hour.

What is the direct labor quantity variance in July?

A. $4,880 favorable

B. $4,800 unfavorable

C. $3,280 unfavorable

D. $4,880 unfavorable