What is the direct-labor price variance


Berea Company produces 2,500 units. Each unit was expected to require 2 labor hours at a cost of $10 per hour. Total labor cost was $55,250 for 4,750 hours worked. Direct labor is measured in hours. What is the direct-labor price variance?