What is the difference between the eacs for upgrading and


In evaluating projects, LeadTech’s engineers use a rate of 15%. One year ago a robotic transfer machine was installed at a cost of $38,000. At the time, a 10-year life was estimated, but the machine has had a downtime rate of 28%, which is unacceptably high. A $12,000 upgrade should ?x the problem, or else a labor-intensive process costing $3,500 in direct labor per year can be substituted. The plant estimates indirect plant expenses at 60% of direct labor, and it allocates front of?ce overhead at 40% of plant expenses (direct and indirect). The robot has a value in other uses of $15,000. What is the difference between the EACs for upgrading and switching to the labor-intensive process?