What is the critical path for this project what is the


The marketing department at Bellevue University is working on a project with the following information. The Activity Time is also referred to as the Normal Activity Time and is the time it takes to complete the activity based on the normal times. The Crash Time is the time it takes to complete the activity if this activity is crashed.

ActivityImmediate PredecessorsActivity Time (Days)Activity Cost (Total)Total Time After Crashing (Days)Activity Crash Cost (Total)

A--6$10,0004$12,000

B--4$5,5002$7,300

CA, B3$6,0002$7,500

DC6$4,0004$6,400

EC4$3,5002$5,100

a) What is the critical path for this project, what is the project completion time, how much total work time (in days) is required for this project, and what is the cost for completing this project using the Activity Time? Also identify the slack time for each path. The slack time for each path should be based on the time to complete the critical path.

b) Suppose that the school wants to complete the project in 13 days by crashing the most economical activity. Which activity(ies) should it crash and how much will the project cost increase?

Solution Preview :

Prepared by a verified Expert
Business Management: What is the critical path for this project what is the
Reference No:- TGS01717304

Now Priced at $20 (50% Discount)

Recommended (92%)

Rated (4.4/5)