What is the critical path


Discussion:

Q: According to the data in the table, what is the critical path?

Activity | Immediate Predecessor | Optimistic Time | Most Likely Time | Pessimistic Time
A - 2 8 14
B - 8 8 8
C A 9 9 18
D B 11 11 17

Options:
A, B
A, C
B, D
A, B, C, D
none of the above

 

Solution Preview :

Prepared by a verified Expert
Basic Statistics: What is the critical path
Reference No:- TGS01898604

Now Priced at $20 (50% Discount)

Recommended (92%)

Rated (4.4/5)