What is the completely accelerated project duration after


A company has developed a project and is interested in accelerating the schedule if possible. Below network diagram and tables show all information needed.Partial crashing is available.

1905_What is the completely accelerated project duration.png

1. For the network, how many potential paths exist?

2. For present schedule, how long will project take?

3. What activity should be crashed first to accelerate the project by 1 day?

4. What activity should be crashed next to accelerate the project by another day?

5. What is the completely accelerated project duration after maximum crashing?

6. What is the total additional cost for reducing the duration by the maximum?