What is the capitalized worth of the project


Problem

A city plans to upgrade its storm water management infrastructure by installing new pipes. The installation costs 2.1 million dollars and the annual maintenance cost is $14,000. Every 8 years, the system needs to be fully examined which requires a fixed management and material cost of $35,000 and a variable labor cost at the rate of $27/hr. 16 full time (working 8 hours per day) workers will be employed for 70 days for this task. If the infrastructure has a life time of 96 years and the city's interest rate is 5%,

i. What is the capitalized worth of the project (in millions)?
ii. What is the EUAC of the infrastructure (in million dollars)?

Request for Solution File

Ask an Expert for Answer!!
Microeconomics: What is the capitalized worth of the project
Reference No:- TGS03322218