What is the capacity of the facility pcweek what is the


Provide all steps

GIVEN:

- 9 workstations (each operator is responsible for three of them)

- Hourly cost of direct labor is 15$/hr

- The set up time required is 6 hrs and production time for each unit is 6 mins

- The initial coat of facility’s machines were $600,000 with 15% interest rate and with useful life of 6 years

- The working shift for operators is 8hr/day, 5days a week (50 weeks a year)

- The repair team has a crew of three working 8hr/day, 6 days a week (50 weeks)

- The machines are 15% down during the operations periods due to breakdowns

- The cost of each repair crew member is 21$/hr

- The repair team and machine have 20% factory over head

- The direct labor has 50% factory over head

- Production has 20 hrs of nonoperational time/machine

- The current order quantity is 20,000 pc

- number of operations is one

-utilization is one

ASKED:

What is the capacity of the facility (pc/week)

What is the actual output quantity of the facility (pc/week)

What is the MLT of the order (hr)

What is the hourly cost rate of a workstation ($/hr)

With 15% mark up, how much will be the customer charged for each unit of product (total raw material cost: $26750 and total tooling cost: $15600)

Request for Solution File

Ask an Expert for Answer!!
Operation Management: What is the capacity of the facility pcweek what is the
Reference No:- TGS02885200

Expected delivery within 24 Hours