What is the breakeven quantity what is the total cost at


The Green Machine Manufacturing Company has the option to make or buy a component part for one of its lawnmowers. The annual requirement is 25,000 units. A supplier is able to supply the parts for $12.25 per piece. Green Machine estimates that it will cost $700 to prepare the contract with the supplier. To make the parts in-house, Green Machine must invest $100,000 in capital equipment. They estimate it will cost $9.00 per piece to produce the part in-house. Carry all calculations out to two decimal places.

1. What is the breakeven quantity?

A) Less than or equal to 30,000

B) Greater than 30,000 but less than or equal to 35,000

C) Greater than 35000 but less than or equal to 40,000

D) Greater than 40,000 but less than or equal to 45,000

E) Greater than 45,000

2. What is the total cost at the breakeven point?

A) Less than or equal to $365,000

B) Greater than $365,000 but less than or equal to $370,000

C) Greater than $370,000 but less than or equal to $375,000

D) Greater than $375,000

3. If the demand is 25,000 units, should Green Machine make or buy the part?

A) Buy the part

B) Make the part

C) Both

D) Neither

E) Not enough information

4. What is the cost savings from making the correct decision?

A) Less than or equal to $20,000

B) Greater than $20,000 but less than or equal to $25,000

C) Greater than $25,000 but less than or equal to $30,000

D) Greater than $30,000 but less than or equal to $35,000

E) Greater than $35,000

Request for Solution File

Ask an Expert for Answer!!
Operation Management: What is the breakeven quantity what is the total cost at
Reference No:- TGS02885266

Expected delivery within 24 Hours