Garman observes a worker assembling peanut valve and records the data displayed in the table: time (seconds) = 10, 15, 20. observations = 18, 25, 17.

1) what is the average time for this job element%

2) what is the normal time for the job element if the the rating factor is 75%

3) what is the standard time for this job element if the allowance for the process is 20%