What is the appropriate reorder point quantity


Problem:

A newspaper publisher uses roughly 850 feet of baling wire each day to secure bundles of newspapers while they are being distributed to carriers. The paper is published Monday through Saturday. Lead time is six workdays.

Required:

Question 1) What is the appropriate reorder point quantity, given that the company desires a service level of 95 percent, if that stockout risk for various levels of safety stock is as follows: 1,500 feet, .10; 1,700 feet, .05; 2,100 feet, .02; and 2,400 feet, .01?

Solve the problem and show all work.

Request for Solution File

Ask an Expert for Answer!!
Operation Management: What is the appropriate reorder point quantity
Reference No:- TGS0880622

Expected delivery within 24 Hours