Question - On May 1, 2011, Green Construction Company entered into a fixed-price contract to construct an apartment building for $3,000,000. Green appropriately accounts for this contract under the percentage-of-completion method. Information relating to the contract is as follows:

2011 2012

At December 31:

Percentage of completion ........ 20% 60%

Estimated costs at completion ... $2,250,000 $2,400,000

Income recognized (cumulative) .. $ 150,000 $ 360,000

What is the amount of contract costs incurred during the year ended December 31, 2012?

a. $600,000

b. $960,000

c. $990,000

d. $1,440,000