What is the actual cost ac for the project whats the


You have just taken over a project from another project manager. Incomplete information is available to you on the project status. You have been told that the cost performance index (CPI) = .92, the earned value (EV) = $322,000 and the planned value (PV) = $180,000. What is the actual cost (AC) for the project? What's the schedule variance (SV) for the project? What about the SPI and the CSI?