What is estimate at completion


Marcy is managing a project for her company. Her project's budget is $250,000. She has calculated the cost performance index (CPI) to be .91 and her costs are $175,000. What is Marcy's estimate at completion (EAC)?

A. $115,750
B. $275,000
C. $265,000
D. $250,000