What is centurys final payment on may 6 assume no


On March 30, Century Television received an invoice dated March 28 from ACME Manufacturing for 50 televisions at a cost of $125 each. Century received a 10/4/2 chain discount. Shipping terms were FOB shipping point. ACME prepaid the $70 freight. Terms were 2/10 EOM. When Century received the goods, 3 sets were defective. Century returned these sets to ACME. On April 8, Century sent a $150 partial payment. Century will pay the balance on May 6. What is Century's final payment on May 6? Assume no taxes.

Request for Solution File

Ask an Expert for Answer!!
Econometrics: What is centurys final payment on may 6 assume no
Reference No:- TGS01416772