What is activity rate for machining activity cost pool


Response to the following problem:

Hickory Company manufactures two products"14,000 units of Product Y and 6,000 units of Product Z. The company uses a plant wide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z:

Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity

Machining ............................... Machine-hours $200,000            10,000 MHs

Machine setups ...................... Number of setups $100,000        200 setups

Production design ................... Number of products $84,000       2 products

General factory ....................... Direct labor-hours $300,000      12,000 DLHs

Activity Measure Product Y Product Z

Machining ............................... 7,000      3,000

Number of setups ................... 50          150

Number of products ................ 1              1

Direct labor-hours ................... 8,000      4,000

QUESTIONS:        

1. What is the company's plantwide overhead rate?

2. Using the plantwide overhead rate, how much manufacturing overhead cost is allocated to Product Y? How much is allocated to Product Z?

3. What is the activity rate for the Machining activity cost pool?

4. What is the activity rate for the Machine Setups activity cost pool?

5. What is the activity rate for the Product Design activity cost pool?

6. What is the activity rate for the General Factory activity cost pool?

7. Which of the four activities is a batch-level activity? Why?

8. Which of the four activities is a product-level activity? Why?

9. Using the ABC system, how much total manufacturing overhead cost would be assigned to Product Y?

10. Using the ABC system, how much total manufacturing overhead cost would be assigned to Product Z?

11. Using the plantwide overhead rate, what percentage of the total overhead cost is allocated to Product Y? What percentage is allocated to Product Z?

12. Using the ABC system, what percentage of the Machining costs is assigned to Product Y? What percentage is assigned to Product Z? Are these percentages similar to those obtained in question 11? Why?

13. Using the ABC system, what percentage of Machine Setups cost is assigned to Product Y? What percentage is assigned to Product Z? Are these percentages similar to those obtained in question 11? Why?

14. Using the ABC system, what percentage of the Product Design cost is assigned to Product Y? What percentage is assigned to Product Z? Are these percentages similar to those obtained in question 11? Why?

15. Using the ABC system, what percentage of the General Factory cost is assigned to Product Y? What percentage is assigned to Product Z? Are these percentages similar to those obtained in question 1 ? Why?

Solution Preview :

Prepared by a verified Expert
Cost Accounting: What is activity rate for machining activity cost pool
Reference No:- TGS02082434

Now Priced at $30 (50% Discount)

Recommended (92%)

Rated (4.4/5)