What interest rate should be used to calculate the present


A municipality has just completed construction of a bridge. It was defined that operation and maintenance (O&M) of this bridge will cost the city $20,000 for the first year with a 5% increase each year thereafter for the next 4 years. The bank rate is 7.5% a year. What interest rate should be used to calculate the present worth of annual expenditures on O&M during the upcoming five year period following the completion of the bridge?

Solution Preview :

Prepared by a verified Expert
Business Economics: What interest rate should be used to calculate the present
Reference No:- TGS02809525

Now Priced at $10 (50% Discount)

Recommended (93%)