Question: Your earned value analysis calculates, "The PV was $240, the EV is $230, and the AC is $250, so we have a CV of $-20 and an SV of -$10." What does this information tell you about this project? What else might you need to know? Explain this as though you were presenting to someone who does not understand the earned value terminology.