What does diseconomies of scale


What does diseconomies of scale? mean?

A. Adding more people to an already late project will make it later.

B. Adding people to a project that is on time will move the completion date ahead by? 0.51%.

C. Adding people to a late project can accelerate the project to on time.

D. For every person added to a late? project, the expected completion date moves up the scale of diseconomy by a factor of 1.325. E. For every day the project is? late, the organization will suffer financial lose following this scale.