What cycle time will provide an output rate of 75 tires per


An assembly line at the Yokohama Plant in West Point has 22 tasks is to be balanced to produce a special variety of tires. The longest task is 5.6 minutes, and the total time for all tasks is 27 minutes. The line will operate for 480 minutes per day. What cycle time will provide an output rate of 75 tires per day?