1. What are the two ways of balancing capacity available and load? Which one do you prefer and why?

2. If the time remaining to complete a job is 10 days and the lead time remaining is 12 days, what is the critical ratio? Is the order ahead of schedule, on schedule, or behind schedule? Explain your answer.