What are the three activity cost pools


A company uses activity-based costing to determine the costs of its three products: A, B and C. The budgeted cost and activity for each of the company's three activity cost pools are shown in the following table:



Budgeted Activity
  Activity Cost Pool Budgeted Cost Product A Product B Product C
  Activity 1 $270,750 11,500 14,500 31,000
  Activity 2 $221,000 12,500 26,000 13,500
  Activity 3 $157,500 3,600 2,100 2,700

How much overhead will be assigned to Product B using activity-based costing?


$218,750

$255,250

$175,250

$649,250

$270,750

Request for Solution File

Ask an Expert for Answer!!
Accounting Basics: What are the three activity cost pools
Reference No:- TGS0673607

Expected delivery within 24 Hours