What are the net requirements


The MPS calls for 120 units of Product X. There are currently 30 of Product X on hand. Each X requires 4 of Component Y. There are 20 units of Y on hand.

What are the net requirements for X?
What are the gross requirements for Y?
What are the net requirements for Y?

The MPS call for 100 units of Product X. There are currently 60 of Product X on hand. Each X requires 2 of Part Y. There are 30 units of Y available.

What are the net requirements for X?
What are the gross requirements for Y?
What are the net requirements for Y?